Walker Movements Truck Workshop

Client M Snutch Builders
Contract value £260,000.00
Date June 2013
Status Complete

Brief
Hoyes Roofing & Cladding submitted a successful tender for the refurbishment of a disused brickworks. The project included removal of roof sheeting and cladding on 3 seperate buildings, one being sheeted in asbestos. Asbestos Removal was carried out in house by UKATA trained personnel.

Once major steel work alterations were complete, Hoyes Roofing & Cladding provided the specification packages for all 3 buildings.

• The roofing material chosen was a Kingspan RW panel.
• The cladding package chosen by the client was a Euroclad 32/1000 built up system in Prisma silver, with anthracite flashings and rainwater goods to match the clients existing sites.

Due to the volume of this particular contract, the timespan was considerably longer due to the initial stripping of the existing buildings. However, Hoyes Roofing & Cladding completed the job within agreed timescales.